4.1 Introduction
----------------
This chapter provides the laboratory hardware requirements needed to
deploy the reference implementation. These requirements represent a
minimum set of requirements, where different labs may have hardware or
capabilities exceeding these minimum specifications.
The lab provides a set of physical servers, supported by a dedicated
network infrastructure. Users should be provided access to the servers,
their operating systems, and out-of-band management (i.e. IPMI, IDRAC,
ILO, etc.).
.. _42-lab-requirements:
4.2 Lab Requirements
--------------------
Labs are organized into one or more *Pods*, where the *Pod* provides the
complete set of resources [servers and network(s)] necessary to support
the reference implementation installation and operation.
A CNTT compliant *Pod* shall meet the following requirements.
1. One (1) physical server dedicated as a Jump / Test Host
2. Six (6) physical servers, serving as either compute or controllers
3. A configured network topology allowing for: Out-of-Band Management,
Admin, Public, Private, and Storage Networks
The Jump Host / Test Host system will be utilized to install and manage
the operation of the *Pod*. For example, the system can be used to host
the installer software used to deploy and configure OpenStack on the
other physical servers. Once installed, the system may be used to run
test automations or it may be used to generate test traffic intended to
measure the performance of a VNF operating within the *Pod*. To support
these operations, the physical server provided for the Jump / Test Host
shall meet the same hardware requirements as compute / controller, as
outline below. In this context, the system may be considered as a
miscellaneous use or general purpose system.
.. _421-physical-server-requirements:
4.2.1 Physical Server Requirements
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
Each server shall meet the following minimum specifications:
- **CPU**
- 2x x86_64 CPU sockets (both populated), providing 24 cores each,
48 simultaneous multi-threads (SMT), at 2.2 GHz
- **Memory**
- 512 GB RAM
- **Storage**
- 3.2 TB SSD via SATA 6 Gbps
- Storage should present as at least 3 or more disks to the OS,
allowing for usage as CEPH storage nodes, or similar.
- **Network Interfaces** (note 1)
- 4x 25 Gbps Ethernet Ports, implemented as two separate dual port
NICs
- Out-of-band Management Port
Note 1: At least 1 network interface must be capable of performing PXE
boot and that network must be available to both the Jump / Test Host and
each physical server.
.. _422-lab-network-hardware--topology:
4.2.2 Lab Network Hardware & Topology
-------------------------------------
Labs that are hosting multiple *Pods* should utilize a leaf / spine
topology when interconnecting *Pods* or physical servers. This is
especially important in the cases where the physical servers
constituting a *Pod* are not located in the same physical rack or are
not connected to the same leaf switch. At least one leaf switch will be
provided for each *Pod*, with interface speeds matching the above server
specifications. In this context, the reference to the single leaf refers
to the logical appearance of switch, compared to topologies providing 2
or more leaf switches to provide high availability.
Leaf switches must provide interfaces matching the physical server
specifications above and northbound (spine connections) of 100 Gbps
connections. Spine switches must provide the corresponding 100 Gbps
interfaces to each leaf switch. The minimum requirement is one spine
switch.
The minimum networking configuration must provide at least VLANs to
partition the various networks required for the reference implementation
deployment and separation of each *Pod*, if multiple *Pods* are hosted
within the labs.
The *Pod* network topology should provide at least 2 networks with
preallocated IP addressing schemes for the *out-of-band management*
network and the *Public* network. The *Public* network must be able to
reach / access the public Internet. At least IPv4 addresses must be
available, ideally IPv6 address space should also be supported.
Remote users shall access the lab via a VPN gateway, that shall also
provide basic security and separation from the public Internet. Both the
*Public* and *out-of-band management* networks shall be accessible
through the VPN connection.
**EDITORS NOTE: Provide a figure showing the basic lab topology, include
the VPN, Pod / Servers, Switch, and management / public networks.**
.. _44-lab-use-guidelines:
4.4 Lab Use Guidelines
----------------------
**SETUP & Maintenance**
OPNFV will facilitate the need for lab procurement, as required, for
projects which come into their front door for verification and
validation.
Individual companies that donated a lab would be responsible for setup
and maintenance of a community lab. Labs, once setup, will be shared and
posted in a wiki
`https://wiki.opnfv.org/display/pharos/Community+Labs `__.
The wiki will contain information such as:
- Lab Location
- Number of physical and virtual PODS which are available
- Contact person
- Policy info for use
- Access instructions, include VPN
- Lab Topology
- Resource Availability
**N+1 Labs Use Strategy**
The "lab" concept could mean one physical POD or multiple PODs in a
community lab. In practice, a person requesting a lab can apply for
multiple PODs, where POD 1 can be "Lab 1", POD 2+3 can be "Lab 2", etc,
all subject to the availability of PODs. Each "Lab" can be used for
different purpose such as "Reference Implementation (RI) Lab 1" (POD 1),
"RI Lab 2" (POD 2+3), etc.
The requester for labs needs to know only the number of PODs that are
needed. Then, apply for use of PODs according to the requirement.
Talk to the Lab Owners if special hardware or topology requirements are
needed, such as special NIC or hardware accelerators or if 8 servers in
one POD is a different default setting from the lab settings. The Lab
Owner will check to see if lab config changes can be made to accommodate
the test need.
**Lab Quantities and Duration of Lab Use**
There is no limit to the number of labs which can be secured, or the
duration. The limiting factor is resource available. Lab Owners reserve
the right to reclaim underutilized labs and reassign to other teams
where there is demand for labs. It is important that the Lab User have a
schedule and plan in place to utilize the labs to retain the lab for
testing.